Order TED/182/2026 establishes minimum services in the electricity sector due to the general strike called by the CGT in Andalusia, Ceuta, and Melilla on March 8, 2026 (00:00 to 24:00). It requires full availability of specific combined cycle plants (Algeciras 3, Arcos de la Frontera 1 and 2, Campo de Gibraltar 1 and 2, Cristóbal Colón 4, Málaga, Palos de la Frontera 1, 2 and 3, San Roque 1) and the generating equipment in Ceuta and Melilla to guarantee supply (First).
Electricity production, transport, and distribution companies operating in Andalusia, Ceuta, and Melilla must ensure continuity of supply and system stability (Art. 2 RD 1170/1988). Affected energy groups must maintain the loads derived from the day-ahead and intraday markets for the strike day (Second). Final consumers should not suffer interruptions to production processes or essential activities due to the availability of the specified facilities (First).