Redexis Infraestructuras, SL: 12 months to build new biomethane connection in Zaragoza

The Directorate General for Energy Policy and Mines has granted administrative authorisation and approved the execution project for a new connection point on the Zaragoza-Calatayud gas pipeline. The objective is to enable the injection of biomethane from the GIA EnR V SLU plant into the primary transport network. The resolution stipulates that construction must be completed within a maximum period of twelve months from notification.

In 3 key points

  1. Maximum period of 12 months for construction and application for commissioning, under the risk of the authorisation being revoked. (5.ª)
  2. Obligation to obtain prior authorisation for any technical expansion or modification of the facilities. (6.ª)
  3. Duty to provide advance notice of construction start dates and testing to the Government Sub-delegation. (7.ª)

How it affects those involved

For Redexis Infraestructuras, SL, the resolution enables the technical execution of the biomethane connection but imposes a strict 12-month deadline for construction and the application for commissioning, under the risk of the authorisation being revoked. For GIA EnR V SLU, it ensures the operational viability of its production plant by providing the necessary injection point. The Government Sub-delegation in Zaragoza holds the power of inspection and control during the execution of the works.

Lifecycle

2026-09-18PublishedPublished in the BOE
Official text Based on BOE data (boe.es). Information, not advice.

Does this provision affect you?

The administrative team reviews your specific situation.

Talk to the administrative team
This analysis is informational only and does not constitute legal advice or create a client-adviser relationship. BM Consulting.
Email
Contact