V1052-26 13 May 2026 · SG de Impuestos sobre el Consumo
IVA · inversión del sujeto pasivo

Investment of passive party applies to final installation of electrical substation if considered building or rehabilitation

A company asked whether expanding an electrical substation to connect a hydrogen plant would allow the application of the passive party's investment. The DGT states that provisional installation does not qualify due to its temporary nature, but final installation may qualify if considered building or rehabilitation.

The question raised

Whether the reverse charge mechanism in Value Added Tax, provided for in Article 84.One, 2, letter f) of Law 37/1992, is applicable.

The DGT's ruling

The provisional installation does not constitute a building as it is temporary and dismantlable, therefore the reverse charge mechanism does not apply. The definitive installation will apply the reverse charge if it is capable of autonomous use (building) or if it is carried out as a rehabilitation of the existing substation under the requirements of Article 20.One.22 of Law 37/1992. In both cases, the electricity company shall be the taxable person as it is the business recipient.