Concessions following a void tender may qualify for the RIC

The application of the Canary Islands Investment Reserve (RIC) requires that investments are made under market conditions and through competitive bidding. One of the recurring doubts in the Canary Islands investment sector was whether the award of an administrative concession through a negotiated procedure, after a previous tender had been declared void, maintained the competitive character necessary to access this tax incentive.

What the DGT has ruled

The Directorate General of Taxes (DGT) has determined that administrative concessions are considered to be acquired under market conditions when they are reached through the negotiated procedure without advertising provided for in the Public Sector Contracts Law, provided that this is the consequence of a previous competitive bidding process that resulted in no award.

For this investment to be eligible for the RIC, the administration establishes two fundamental conditions:

  • The initial conditions of the original contract must not be substantially modified.
  • All other requirements established in Article 27 of Law 19/1994 must be met.

What this means for you

This criterion provides legal certainty to companies operating in the archipelago that depend on the award of administrative concessions to build their investment base. If your investment strategy in the Canary Islands involves the acquisition of concessions, the fact that the initial public tender process does not result in an award does not automatically nullify the possibility of applying the RIC, provided that the negotiation mechanism provided for in public procurement regulations is used.

What you should do

Companies must ensure that the procurement file clearly reflects the causal link between the void tender and the subsequent negotiated procedure. It is necessary to verify that the final contract conditions do not deviate from the conditions of the initial tender to prevent the Administration from questioning the nature of the investment. It is recommended to strictly monitor compliance with the requirements of Law 19/1994 to guarantee the correct application of the incentive.

Frequently asked questions

Is the right to the RIC lost if the initial public tender is declared void?
No, provided that the concession is acquired through a negotiated procedure without advertising and the initial conditions are not substantially altered.
Which regulations govern this criterion?
The resolution is based on Law 19/1994 and Law 9/2017.
Official binding ruling V6009-26