Renewable energy companies: requirements and €80/kW guarantee for access to the Mudéjar 400 kV node

This Order regulates the procedure for granting evacuation access capacity to the electricity grid at the Mudéjar 400 kV just transition node. The process is based on the order in which applications are submitted and requires a financial guarantee of €80.00 per installed kW to ensure project maturity and compliance with socio-economic commitments. This regulation amends base 23 of Order TED/1182/2021 to facilitate the energy transition in areas affected by power plant closures.

In 3 key points

  1. Financial guarantee of €80.00/kW installed to ensure the execution and maturity of the application (texto fuente)
  2. Allocation is prioritised according to the date of correct submission of the application (texto fuente)
  3. The €80/kW guarantee is additional to and independent of the €40/kW guarantee in RD 1183/2020 (texto fuente)

How it affects those involved

For renewable energy project developers, access to the Mudéjar 400 kV node is subject to submitting applications based on a priority criterion of submission date. Interested parties must face an additional financial burden through a guarantee of €80.00 per installed kW, which is independent of the €40 per kW guarantee already provided for in Royal Decree 1183/2020. Compliance with socio-economic requirements and the application for access and connection permits are essential for the allocation of capacity.

Lifecycle

2026-11-11PublishedPublished in the BOE
Official text Based on BOE data (boe.es). Information, not advice.

Does this provision affect you?

The administrative team reviews your specific situation.

Talk to the administrative team
This analysis is informational only and does not constitute legal advice or create a client-adviser relationship. BMC.
Book your free first meeting